The real 8-week ADU schedule
Langone Site Services completes most ADU builds — from the 384 sq ft Bean to the 981 sq ft Ellas Retreat — in 8 weeks on standard sites with utilities at the property line and permits in hand. Here's the exact weekly breakdown.
Week 1–2: Site prep and foundation
- Mobilize excavation crew and equipment (we own our fleet, no rental delays)
- Clear, strip topsoil, rough grade to plan
- Excavate foundation, prep gravel base
- Install under-slab utilities (water, sewer/septic, electrical conduit)
- Form and pour monolithic slab
- DEP erosion controls installed from day one
Week 3: Framing and roof system
- Pre-cut framing package delivered
- Walls stood and sheathed
- Roof trusses set, decked, and shingled (30-year architectural)
- ZIP wall and roof system tape and seal complete
Week 4: Exterior envelope
- Windows and doors installed (Matthew's Brothers)
- Vinyl siding hung
- Exterior trim complete
- Rough-in for exterior utilities
Week 5: Rough-in trades
- Electrical rough-in
- Plumbing rough-in
- Mini-split HVAC installation (Mitsubishi ductless system)
- Starlink wiring run
- Inspections scheduled and passed
Week 6: Insulation and drywall
- R23 wall and R49 ceiling insulation
- Sheetrock hung, taped, and primed
- First coat of paint on ceilings and walls
Week 7: Finish carpentry and fixtures
- Tongue-and-groove pine ceilings installed
- LVP flooring throughout
- Cabinets set, granite counters installed
- Delta plumbing fixtures installed
- Recessed LED lighting
- Interior doors hung and trimmed
Week 8: Paint, punch list, and handoff
- Final paint coat
- Full punch-list walk with client
- Appliance installation (if included in package)
- Final inspections + certificate of occupancy
- Handoff walkthrough
Why we hit this schedule
We own our site-work equipment, so our excavation timeline doesn't depend on rental availability or a sub's schedule. The specialty trades (plumbing, electrical) are contracted under our prime so we control the critical path. And we communicate weekly — clients get a Friday text with the week's progress + next week's plan.
What shifts the timeline
- Permits delayed. If the town sits on the application, Week 1 can't start.
- Major weather event. Nor'easters in November or May can shift excavation a week.
- Custom design changes. Requested after permits issue, add 1–3 weeks.
- Long utility runs. Properties without utilities at the line add a week of trenching.
Want an 8-week build on your lot? Compare all 7 ADU models, start with instant pricing, or book a free build consult.
Skip the guesswork — get instant pricing.
Our 2-minute calculator gives you a real ballpark for any project type in Maine or New Hampshire.
Price My Project